ACHIEVEMENT OF WORKS UNDER PWD , AIZAWL

1. Name of work : Construction of S.P Office at Aizawl
  a) Sanctioned Amount : Rs.71.69.00 lakhs
  b) Expenditure : Rs.83.45.00 lakhs
  c) Date of commencement : 28-4-1998
  d) Date of completion : 7/3/2000
  e) Plinth area : 1,345.00m2
  f) Purpose

To accommodate the SP, Addl. SP (Traffic) DSP (wireless), VDO store, ASP traffice or stationary room as the bld presently is not sufficient

2. Name of work : Construction of additional M.L.A  Hostel at Tuikhuahtlang, Aizawl.
  a) Sanctioned Amount : Rs.175.52 lakhs
  b) Expenditure : Rs.129.40 lakhs
  c) Date of commencement : 18.11.96
  d) Date of completion : 24.11.99
  e) Plinth area : 1870.00Sqm.
  f) Purpose As the existing M.L.A Hostel is not sufficient, additional  M.L.A Hostel  is required.
3 Name of work : Construction of Consumer Building at Tuikhuahtlang, Aizawl.
  a) Sanctioned Amount : Rs.32.56 lakhs
  b) Expenditure : Rs.26.576 lakhs
  c) Date of commencement : 31.3.2003
  d) Date of completion : Completed except painting.
  e) Plinth area : 479.40 Sqm
  f) Purpose : To accommodate the District Forum , members and Judges, court room, drivers room, canteen and staff.
4 Name of work : Construction of Circle Office,PWD, building at Ramhlun Veng,Aizawl.
  a) Sanctioned Amount : Rs.90.96 lakhs
  b) Expenditure : Rs.57.95 lakhs
  c) Date of commencement : 31.3.2003
  d) Date of completion : On going work.
  e) Plinth area : 1,397.25 m2
  f) Purpose :

To accommodate PWD offices which are still in private buildings.

5 Name of work : Construction of Finance Secretariat building at Treasury Square, Aizawl.
  a) Sanctioned Amount : Rs.253.58 lakhs
  b) Expenditure : Rs.189.29 lakhs
  c) Date of commencement : 28.10.99
  d) Date of completion : On going work.
  e) Plinth area : 3,657.00m2
  f) Purpose :

To accommodate two Ministers,  two Deputy Secretaries, three   Under Secretaries, Commissioner & Secretary etc.

6 Name of work : Construction of Chief Minister`s Bungalow at Mc Donald Hill,Zarkawt,Aizawl.
  a) Sanctioned Amount : Rs.547.52 lakhs
  b) Expenditure : Rs237.9 lakhs
  c) Date of commencement : 15.12.95
  d) Date of completion : 12.2.2002
  e) Plinth area : 1376.00 Sqm.
  f) Purpose :

To accommodate the Chief Minister and his family as the previous C.M Bungalow is old and not fit for residence.

7 Name of work : Construction of Chief Minister`s
  Secretariat at Mc Donald Hill, Zarkawt, Aizawl.
  a) Sanctioned Amount : Rs.264.57 lakhs
  b) Expenditure : Rs.147.47 lakhs
  c) Date of commencement : 21.2.2000
  d) Date of completion : 11.5.2002
  e) Plinth area : 1218.6 Sqm
  f) Purpose :

building is old and far from the Chief The old Chief Minister`s Secretariat Minister`s Bungalow. Hence a new building  is necessary near the new C.M Bungalow.

8 Name of work : Construction of New Raj Bhavan
  at Khatla, Aizawl.
  1) Ceremonial Wing:    
  a) Sanctioned Amount : Rs.147.76 lakhs
  b) Date of commencement : 11.11.2002
  c) Date of completion : On going work.
  d) Plinth area : 1252.04 m2
  e) Purpose

room Conference room, DHall and Security Personal room. urbar To provide Banquet Hall,Pre-function

  2) Governor`s Secretariat and Office.
  a) Sanctioned Amount : Rs.128.91 lakhs
  b) Date of commencement   14.10.2002
  c) Date of completion : On going work.
  d) Plinth area : 1476.20 m2
  e) Purpose :

To provide Governor`s Office, Press  Conference, Meeting room, Secretary to Governor room, ADC room, Jt.Secretary`s room, Dy.Secretary`s  room, P.S room, Cypher room & lounge.

  3) Governor`s Residence:    
  a) Sanctioned Amount : Rs.141.84 lakhs
  b) Date of commencement : 13.11.2002
  c) Date of completion : On going work
  d) Plinth area : 1292.20 m2
  f) Purpose to provide residence for the Governor.
c 4) V.V.I.P Guest House:    
  a) Sanctioned Amount : Rs.87.32 lakhs
  b) Date of commencement : 12.11.2002
  d) Date of completion : On going work.
  e) Plinth area : 789.51 m2
  f) Purpose :

To provide room & accommodation  for visiting V.V.I.P Guests and their staffs.

9 Name of work : Construction of New Secretariat
  Building at Khatla.    
  a) Sanctioned Amount : Rs.1395.74 lakhs
  b) Expenditure : 11.16 lakhs
  c) Date of commencement : 26.9.2002
  d) Date of completion : On going work
  e) Plinth area : 13020.75 m2
  f) Purpose : To accommodate 18 nos of Minister`s rooms 23 rooms for Commissioner & Secretary & above, conference hall & staff rooms.
10 Name of work : Construction of  New Capital Project at Khatla, accommodation building.
  a) Sanctioned Amount : Rs.390.10 lakhs
  b) Expenditure : Rs.389.99 lakhs
  c) Date of commencement : 3.7.2002
  d) Date of completion : On going work.
  e) Plinth area : 4301.32 m2
11 Name of work : Construction of  Soil & Water
  Conservation  Directorate Building.    
  a) Sanctioned Amount : Rs.145.48 lakhs
  b) Expenditure : Rs.124.51 lakhs
  c) Date of commencement : 2.4.2000
  d) Date of completion : 30.3.2002
  e) Plinth area : 1979.90 m2
  f) Purpose :

To accommodate the Directorate Office as the Directorate is functioning in a private building.

12 Name of work : Construction of  Regional Institute of Para Medical & Nursing Home at Zemabawk.
  1) Boy`s Hostel :    
  a) Sanctioned Amount : Rs.107.42 lakhs
  b) Date of commencement : 12.5.88
  c) Date of completion : 15.3.2001
  d) Plinth area : 2145.40 m2
  e) Purpose : To provide accommodation for 107 students.
  2) Administrative Block :    
  a) Sanctioned Amount : Rs.59.13 lakhs
  b) Date of commencement : 12.5.88
  c) Date of completion : 28.3.2000
  d) Plinth area : 1292.50 m2
  e) Purpose : To provide rooms for the Director & staffs.
  3) Academic Building Block-I :    
  a) Sanctioned Amount : Rs.140.00 lakhs
  b) Date of commencement : 16.9.88
  c) Date of completion : 2.12.2001
  d) Plinth area : 1524.00 m2
  e) Purpose : To provide class rooms etc. for the institute.
  4) Academic Building Block-II :    
  a) Sanctioned Amount : Rs.78.77 lakhs
  b) Date of commencement : 18.12.2000
  c) Date of completion : 27.3.2002
  d) Plinth area : 835.00 m2
  e) Purpose : To provide class rooms etc. for the institute.
  5) Director`s Quarter :    
  a) Sanctioned Amount : Rs.20.50 lakhs
  b) Date of commencement : 4.3.2002
  c) Date of completion : On going work (98% completed)
  d) Plinth area : 201.20 m2
  e) Purpose : Accommodation for the Director of the institute.
  6) Type-I Quarter (6 units) :    
  a) Sanctioned Amount : 33.43 lakhs
  b) Date of commencement : 7.3.2002
  c) Date of completion : On going work (97% completed)
  d) Plinth area : 271.08 m2
e) Purpose : To provide accommodation for the staffs.
  7) Type-II Quarter (6 units) :  
  a) Sanctioned Amount : 40.27 lakhs
  b) Date of commencement : 7.3.2002
  c) Date of completion : On going work (97% completed)
  d) Plinth area : 330.12 m2
  e) Purpose To provide accommodation for the staffs.
  8) Type-III Quarter (6units) :    
  a) Sanctioned Amount : 54.01 lakhs
  b) Date of commencement : 4.3.2002
  c) Date of completion : On going work (97% completed)
  d) Plinth area : 443.88 m2
  e) Purpose : To provide accommodation for the staffs.
13 Name of Work : Construction of Tourist Home
  at Berawtlang.    
  a) Sanctioned Amount : 35.60 lakhs
  b) Date of commencement : 14.8.2000
  c) Date of completion : 28.10.2002
  d) Plinth area : 392.40 m2
  e) Purpose : To provide lodging for tourists visiting Mizoram.
14 Name of Work : Construction of  Sub-Regional
  Science Center at Berawtlang.    
  a) Sanctioned Amount : 115.47 lakhs
  b) Date of commencement : 8.8.2001
  c) Date of completion : On going work (95% completed)
  d) Plinth area : 1140.29 m2
  e) Purpose :  
15 Name of Work : Construction of  Prayer Hall at Berawtlang.  
  a) Sanctioned Amount : 23.70 lakhs
  b) Date of commencement : 10.10.2000
  c) Date of completion : 2.8.2002
  d) Plinth area : 415.75 m2
  e) Purpose To provide place for praying for visitors
16 Name of Work : Construction of  New Tourist Lodge at Chaltlang.
  a) Sanctioned Amount : 124.93 lakhs
  b) Date of commencement : 4.10.2000
  c) Date of completion : On going work (80% completed)
  d) Plinth area : 1786.00 m2
  e) Purpose : To provide lodging for tourists.
13 Name of Work : Construction of  Maternity Ward at I.T.I.
  a) Sanctioned Amount : 25.04 lakhs
  b) Date of commencement : 26.6.2001
  c) Date of completion : 23.4.2002
  d) Plinth area : 310.40 m2
  e) Purpose :

To provide  maternity ward for the local people so that they need not go to the Civil Hospital which is far from the locality.

14 Name of Work : Construction of  Multipurpose
  Hall at Berawtlang.    
  a) Sanctioned Amount : 51.24 lakhs
  b) Date of commencement : 8.4.2002
  c) Date of completion : On going work (75% completed)
  d) Plinth area : 259.57 m2
  e) Purpose : To provide place for conducting functions.
15 Name of Work : Construction of  C.T. Scan Building
  at Civil Hospital.    
  a) Sanctioned Amount : 55.22 lakhs
  b) Date of commencement : 5.3.2003
  c) Date of completion : On going work (70% completed)
  d) Plinth area : 415.00 m2
  e) Purpose :

To provide room for C.T.Scan machine & staff at the Civil Hospital.

16 Name of Work : Construction of  Administrative
  Block for P.U. College.    
  a) Sanctioned Amount : 54.19 lakhs
  b) Date of commencement : 7.8.2000
  c) Date of completion : 3.4.2002
  d) Plinth area : 750.00 m2
  e) Purpose : To provide rooms for the Principal and his staffs.
21 Name of Work : Construction of  Education Technology Cell Studio & Science Laboratory for SCERT at Chaltlang
  a) Sanctioned Amount : 95.44 lakhs
  b) Date of commencement : 15.9.99.
  c) Date of completion : 14.8.2002
  d) Plinth area : 1150.07 m2
  e) Purpose :

To provide space for laboratory equipments and education technology cell.

22 Name of Work : Construction of  Directorate of Technical Education Building at Chaltlang.
  a) Sanctioned Amount : 54.62 lakhs
  b) Date of commencement : 15.9.2002
  c) Date of completion : On going work (20% completed)
  d) Plinth area : 745.00 m2
  e) Purpose : To provide rooms for the Director and his staffs.
23 Name of Work : Construction of  College  of   Teachers Education Building at Republic Veng.
  a) Sanctioned Amount : 90.94 lakhs
  b) Date of commencement : 14.1.2002
  c) Date of completion : On going work (70% completed)
  d) Plinth area : 1412.00 m2
  e) Purpose :

To provide office and class rooms for the college of teachers education.

24 Name of Work : Construction of  District L.A.D Office at Ramhlun.
  a) Sanctioned Amount : 95.14 lakhs
  b) Date of commencement : 26.11.98
  c) Date of completion : 18.10.2001
  d) Plinth area : 1074.00 m2
  e) Purpose :

To provide rooms for the District Local Administration Officer & his staffs.

25 Name of Work : Construction of  Collegiate
  Boy`s Hostel at Luangmual.    
  a) Sanctioned Amount : 45.18 lakhs
  b) Date of commencement : 15.4.97
  c) Date of completion : 11.12.2002
  d) Plinth area : 807.90 m2
  e) Purpose : To provide lodging for college student from other places.
26 Name of Work : Construction of  Hindi Training College at Durtlang.
  1) Type-I Quarter (6 units)    
  a) Sanctioned Amount : 23.95 lakhs
  b) Date of commencement : 9.1.2001
  c) Date of completion : 5.4.2002
  d) Plinth area : 336.00 m2
  e) Purpose To provide accommodation for college staffs.
  2) Type-I IQuarter (6 units)    
  a) Sanctioned Amount : 29.90 lakhs
  b) Date of commencement : 9.1.2001
  c) Date of completion : 5.4.2002
  d) Plinth area : 399.00 m2
e) Purpose To provide accommodation for college staffs.
  3) Type-IIIQuarter (6 units)    
  a) Sanctioned Amount : 35.29 lakhs
  b) Date of commencement : 9.1.2001
  c) Date of completion : 5.4.2002
  d) Plinth area :

475.05

  e) Purpose To provide accommodation for college staffs.
  4) Type-IVQuarter (6 units)
  a) Sanctioned Amount : 58.57 lakhs
  b) Date of commencement : 29.5.2001
  c) Date of completion : 95% completed
  d) Plinth area : 856.40 m2
  e) Purpose To provide accommodation for college staffs.
  5) Type-V Quarter (2 units)
  a) Sanctioned Amount : 23.86 lakhs
  b) Date of commencement : 29.5.2001
  c) Date of completion : 24.1.2002
  d) Plinth area : 305.80 m2
  e) Purpose To provide accommodation for college staffs.
  6) Boy`s Hostel :
  a) Sanctioned Amount : 61.89 lakhs
  b) Date of commencement : 9.1.2001
  c) Date of completion : 99% completed
  d) Plinth area : 788.6 m2
  e) Purpose : To provide accommodation for male students.
  7) Girl`s Hostel :
  a) Sanctioned Amount : 61.89 lakhs
  b) Date of commencement : 29.5.2001
  c) Date of completion : 60% completed
  d) Plinth area : 716.64 m2
  e) Purpose To provide accommodation for female students.
  8) Academic Block :    
  a) Sanctioned Amount : 85.18 lakhs
  b) Date of commencement : 9.1.2001
  c) Date of completion : 60% completed
  d) Plinth area : 1565.65 m2
  e) Purpose To provide class rooms etc. for the college.
25 Name of Work : Construction of Women Polytechnic at Durtlang.
   Sanctioned Amount : 79,332,602.06   lakhs
      (Total cost for the whole project)
  1) Main Building :    
  a) Date of commencement : 11.12.2002
  b) Date of completion : 15% completed
  c) Plinth area : 2421.00 m2
  d) Purpose To provide class rooms, rooms for the Principal & staffs, offices. etc.
  2) Hostel Building :    
  a) Date of commencement : not yet started
  b) Date of completion : not yet started
  c) Plinth area : 1747.00 m2
  d) Purpose To provide accommodation for the students.
  3) Multipurpose Building :    
  a) Date of commencement : 27.1.2003
  b) Date of completion : 5% completed
  c) Plinth area : 677.00 m2
  d) Purpose : For conducting functions etc,.
  a) Date of commencement : not yet started
  b) Date of completion : not yet started
  c) Plinth area : 148.00 m2
  d) Purpose : To provide accommodation for the Principal.
  5) H.O.D Quarters (2 units) :    
  a) Date of commencement : not yet started
  b) Date of completion : not yet started
  c) Plinth area : 240.00 m2
  d) Purpose : To provide accommodation for the Head of Department.
  6) Warden`s Quarter :    
  a) Date of commencement : not yet started
  b) Date of completion : not yet started
  c) Plinth area : 100.00 m2
  d) Purpose : To provide accommodation for the Hostel Warden.
  7) Lecturer`s Quarter :    
  a) Date of commencement : not yet started
  b) Date of completion : not yet started
  c) Plinth area : 680.00 m2
  d) Purpose : To provide accommodation for the Lecturers.
  8) ADM & Non teaching staff Quarter-I(4 units)
  a) Date of commencement : not yet started
  b) Date of completion : not yet started
  c) Plinth area : 300.00 m2
  d) Purpose : To provide accommodation for the staffs.
  9) ADM & Non teaching staff Quarter-II(8 units)
  a) Date of commencement : not yet started
  b) Date of completion : not yet started
  c) Plinth area : 440.00 m2
  d) Purpose : To provide accommodation for the staffs.
  10) External development works :    
  a) Date of commencement : 6.1.2003
  b) Date of completion : 20% completed.
28 Name of Work : Construction of LPG Bottling Plant at Mualkhang.
  a) Sanctioned Amount : 80.43 lakhs
  b) Date of commencement :

2002

  c) Date of completion : On going (53.8% completed)
2. Name of work : Construction of additional M.L.A  Hostel at Tuikhuahtlang, Aizawl
  a) Sanctioned Amount : Rs.175.52 lakhs
  b) Expenditure : Rs.129.40 lakhs
  c) Date of commencement : 18.11.96
  d) Date of completion : 24.11.99
  e) Plinth area : 1870.00Sqm.
  f) Purpose

As the existing M.L.A Hostel is not sufficient, additional  M.L.A Hostel  is required