2 - FOUNDATION |
|
Sl No |
Description |
Unit |
Rate |
|
|
|
|
|
|
|
101 |
Brick masonry work in cement mortar 1:3 in foundation complete
excluding pointing and plastering, as per drawing and Technical
Specifications. |
cum |
Rs.3,779.00 |
|
|
|
(Rupees three thousand seven hundred seventy nine) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
102 |
Stone masonry work in cement mortar 1:3 for foundation complete as per
drawing and Technical Specifications. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(a) |
Coursed Rubble Masonry (first sort). |
cum |
Rs.3,284.30 |
|
|
|
|
|
(Rupees three thousand two hundred eighty four and paise thirty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(b) |
Random Rubble Masonry (coursed / uncoursed). |
cum |
Rs.3,371.10 |
|
|
|
|
(Rupees three thousand three hundred seventy one and paise ten) only. |
|
|
|
|
|
|
|
|
|
|
|
|
103 |
Cement concrete for plain concrete / reinforced concrete in open
foundation as per drawing & Technical Specifications. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(a) |
M 15 grade in P.C.C. |
cum |
Rs.3,560.90 |
|
|
|
|
|
(Rupees three thousand five hundred sixty and paise ninety) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(b) |
M 20 grade in P.C.C. |
cum |
Rs.3,901.30 |
|
|
|
|
|
(Rupees three thousand nine hundred one and paise thirty) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(c) |
M 20 grade in R.C.C. |
cum |
Rs.4,073.10 |
|
|
|
|
|
(Rupees four thousand seventy three and paise ten) only. |
|
|
|
|
|
|
|
|
|
|
|
|
|
(d) |
M 25 grade in R.C.C. |
cum |
Rs.4,267.70 |
|
|
|
|
|
(Rupees four thousand two hundred sixty seven and paise seventy) only. |
|
|
|
|
|
|
|
|
|
|
|
|
104 |
HYSD bar reinforcement in foundation complete as per drawing and
Technical Specifications. |
tonne |
Rs.31,868.90 |
|
|
|
(Rupees thirty one thousand eight hundred sixty eight and paise
ninety) only. |
|
|
|