Sl no SOR No Items of Work Measurements Quantity Unit Rate Amount
No L B D Rs.    P Rs.      P
1 149 Providing and laying reinforced cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate  20mm nominal size) excluding cost of centering and shuttering and reinforcement in -
 
 
 
  (b) Columns. 12 3.00 0.35 0.35 4.410
  10 1.00 0.35 0.35 1.225
  2 1.20 0.35 0.35 0.294
  2 3.00 0.35 0.35 0.735
  6.664 cum 3758.80 25048.64
  (c) Beams, suspended floors, roofs having slope upto 15 degree, landings, balconies, shelves, chajjas, lintels, bands, window sills, stair cases, spiral stair cases, cantilevers upto floor five level. Beams :
  3 14.80 0.25 0.45 4.995
  4 8.00 0.25 0.45 3.600
  2 3.10 0.25 0.25 0.388
  8.983
  Slabs :
  1 14.80 9.05 0.14 18.752
    Deduct stairs opening 1 2.40 4.85 0.14 -1.630      
  Deduct top of beams 3 14.80 0.25 0.14 -1.554
  4 8.00 0.25 0.14 -1.120
    Kitchen platform 2 4.30 0.60 0.10 0.516      
  Landing 1 1.88 2.40 0.14 0.632
  Stair cover 1 2.00 3.10 0.10 0.620
  1 3.43 3.10 0.10 1.063
  1 1.50 3.10 0.10 0.465
  17.744
  Stairs :
  2 3.43 1.20 0.15 1.235
      24 1.20 1/2 x 0.27 x 0.144 0.560      
  1.795
  Chajja :
  6 2.60 0.60 0.10 0.936
  6 2.20 0.10 0.10 0.132
  2 1.60 0.60 0.10 0.192
  2 1.20 0.10 0.10 0.024
  2 1.20 0.60 0.10 0.144
  2 0.80 0.10 0.10 0.016
  1.444
  Total 29.965 cum 3778.50 113223.33
    (g) Vertical and horizontal fins, individually or forming box louvres, facias and eaves boards upto floor five level.                
    2 4.00 1.00 0.10 0.800 cum 3817.40 3053.92
2 154 HYSD bars reinforcement for RCC work including straighthening, cutting, bending, placing in position and binding all complete.
 
          Qnty of concrete        
  Column @ 210 kg/m3 of concrete 210 6.664 1399.440
    Beams @ 150 kg/m3 of concrete 150     8.983 1347.375      
  Slab @ 100 kg/m3 of concrete 100 17.744 1774.398
    Stairs @ 120 kg/m3 of concrete 120     1.795 215.361      
    Chajja @ 80 kg/m3 of concrete 80     1.444 115.520      
  Eaves board @ 80 kg/m3 of concrete 80 0.800 64.000
  4916.094 kg
  49.161 qtl 3342.10 164300.77
3 155 Centering and shuttering including strutting, propping, etc.  and removal of form works in -
 
  (c) Columns. 12 4 0.35 3.00 50.400
  10 4 0.35 1.00 14.000
  2 4 0.35 1.20 3.360
  2 4 0.35 3.00 8.400
  76.160 sqm 191.60 14592.26
  (d) Lintels, beams, plinth beams, girders, bressumers and cantilevers, etc. 3 2 0.31 14.80 27.528
  3 1 0.25 14.80 11.100
  4 2 0.31 8.00 19.840
  4 1 0.25 8.00 8.000
  10 0.31 0.25 0.775
  2 3 0.25 3.10 1.550
  68.793 sqm 148.70 10229.52
  (e) Suspended floors, roofs, landings, shelves and their support, balconies and chajjaj, etc.
 
  Slab 1 14.80 9.05 133.940
  2 14.80 0.14 4.144
  2 9.05 0.14 2.534
  2 4.85 0.14 1.358
    Deduct stairs opening 1 2.40 4.85   -11.640      
    Deduct beam bottom area 3 14.80 0.25   -11.100      
  4 8.00 0.25 -8.000
  Kitchen platform 2 4.30 0.60 5.160
  4 4.30 0.10 1.720
  4 0.60 0.10 0.240
  Landing 1 1.88 2.40 4.512
  2 1.88 0.14 0.526
  1 2.40 0.14 0.336
  Stair cover 1 2.00 2.40 4.800
  1 3.43 2.40 8.232
  1 1.50 2.40 3.600
  Chajja 6 2.60 0.60 9.360
  12 2.60 0.10 3.120
  12 0.60 0.10 0.720
  6 2.20 0.10 1.320
  12 2.20 0.10 2.640
  12 0.10 0.10 0.120
  2 1.60 0.60 1.920
  4 1.60 0.10 0.640
  4 0.60 0.10 0.240
  2 1.20 0.10 0.240
  4 1.20 0.10 0.480
  4 0.10 0.10 0.040
  2 1.20 0.60 1.440
  4 1.20 0.10 0.480
  4 0.60 0.10 0.240
  2 0.80 0.10 0.160
  4 0.80 0.10 0.320
  4 0.10 0.10 0.040
  163.882 sqm 218.70 35841.08
 
    (f) Staircases (except spiral staircase) excluding landings. 2 3.43 1.20   8.232      
  4 3.43 0.15 2.058
  24 1.20 0.144 4.147
  48 1/2 x 0.27 x 0.144 0.933
  15.370 sqm 166.30 2556.08
 
  (k) Vertical and horizontal fins individually or forming box, louvres and bends, eaves boards. 4 4.00 1.00 16.000
  2 4.00 0.10 0.800
  16.800 sqm 262.60 4411.68
4 323 Cement concrete flooring 25mm thick with cement concrete 1:2:4 (1 cement : 2 sand : 4 well graded stone aggregate 12.5mm size) finished with a floating coat neat cement including cement slurry etc. complete but excluding the cost of nosing of steps etc.
 
 
 
  1 14.80 9.05 133.940
    Deduct stairs opening 1 4.85 2.40   -11.640      
    Deduct toilet floor 2 1.80 1.60   -5.760      
  116.540 sqm 142.00 16548.68
5 231 Providing Ist class local wood dressed in frames of chaukat for doors, windows, clerestory windows fixed in position.                
 
  D2 4 2.10 0.10 0.08 0.067
  2 1.20 0.10 0.08 0.019
  D 8 2.10 0.10 0.08 0.134
  4 0.90 0.10 0.08 0.029
  D1 4 2.10 0.10 0.08 0.067